Blog

Canada Energy Regulator Denies NGTL Abandonment Application

June 01, 2020

Close

Written By Marie Buchinski and Stephanie Ridge

On May 20, 2020, the Commission of the Canada Energy Regulator denied an application by NOVA Gas Transmission Ltd. (NGTL) for leave to abandon facilities that are part of NGTL’s extensive system of pipeline and facilities in Alberta and British Columbia.

NGTL brought the application primarily on the basis that the facilities to be abandoned were no longer economic. It argued that tolls for contracted volumes were not sufficient to justify the continued operation and maintenance of the facilities, and that continued operation would place an undue burden on NGTL and its rate payers, which was not in the public interest. The Commission disagreed, finding that the application was not in the public interest at this time and that there would be no undue burden on NGTL or its rate payers if the application was denied. The Commission made the following findings: 

Overall, in denying the request for leave to abandon, the Commission considered the economic viability of the specific facilities to be abandoned balanced with any public interest considerations. Importantly, the Commission found that NGTL’s assessment of economic viability was flawed in part because it failed to meaningfully account for the value of the services provided by the facilities to be abandoned. Further, although the Commission was not persuaded that denying the application would lead to an undue burden on NGTL or its rate payers, it also found that NGTL did not attempt to reduce the burden on itself and its shippers, raising further questions about NGTL’s assessment and process that led to the request for leave to abandon. In the end, the Commission was not persuaded that the proposed abandonment was in the public interest at this time, but left open the potential for NGTL to re-apply for abandonment in the future.

Given the Commission’s concerns regarding the application, and NGTL’s submissions that it not only has other smaller facilities on the NGTL System with remaining contracts that meet some of NGTL’s abandonment criteria, but that NGTL expects the number of facilities with significant integrity costs relative to revenues will increase over time, the Commission strongly encouraged NGTL to develop a more effective process to identify and assess facilities for its future abandonment applications where there are matters such as contract terminations and potentially negative impacts on users of the facilities. The Commission provided NGTL with nine points of guidance, suggesting that NGTL’s process for assessing and identifying facilities for abandonment should:

While the decision is directed at NGTL, it provides guidance to all proponents who may be considering applications for leave to abandon CER-regulated facilities. The decision provides guidance on the processes that should be considered by a proponent when it is determining what facilities to abandon, and what factors should be considered in that assessment process, particularly in circumstances where the abandonment will require contract terminations or will cause negative impacts on users.

The Commission’s analysis of the approach used by NGTL to assess the economic feasibility of the facilities and of NGTL’s assessment of undue burden is also instructive. The decision confirms that economic feasibility is not limited to a calculation of revenues and costs, but must also consider other factors, such as the value of the services provided by the facilities to be abandoned.  Assertions of undue burden need to be supported by evidence, including evidence that the proponent looked at options in an effort to reduce the burden, such as through toll changes on the CER-regulated facilities.

Related Links



View Full Mobile Experience