Written By Michael R. Barrett, Leonard J. Griffiths, Adrienne Moore, Keith G. Sutherland
On September 24, 2009, the Ontario government
announced the implementation
of key steps to facilitate the development of
renewable energy projects in Ontario.
While additional details remain to be
released, the steps discussed below provide
important pieces to the Ontario renewable
power regulatory framework.
FIT Program Launch
North America's first comprehensive feed-in-tariff (FIT) program will launch October 1,
2009. There will be two phases to the application
process. Applications received during
the launch period, beginning October 1,
2009, and ending November 29, 2009, will
be prioritized by the Ontario Power Authority
(OPA) in the manner summarized below. Applications
received after the launch period
will be prioritized on a first-come, first-served
basis.
Applications received during the launch
period will be assigned a time stamp in
relative priority to other applications received
during the launch period. Priority will be determined
in the following manner:
- The FIT program draft contract
includes the period within which the
applicant's facility will have to achieve
commercial operation (i.e., three years
for solar and on-shore wind). Each
application received during the launch
period will indicate the number of
days by which the applicant is willing
to reduce that period, labelled COD
Acceleration Days. Applicants with the
highest number of COD Acceleration
Days will receive the highest priority.
- If one or more applications have the
same number of COD Acceleration
Days, priority will be given to the
applicant that scores highest on a four-point
criteria scale. The criteria are:
- is the generating facility renewable
energy approval (REA) exempt
(see below for REA discussion);
- does the project have fixed or
guaranteed equipment pricing;
- evidence of prior management
for similar facilities; and
- financial sufficiency of the
generating facility's ownership.
- If following (a) and (b), one or
more applications have the same
outcomes, priority will be given to
the applicant with the earliest date
that the project secured access rights
to the project's location. Access
rights may be achieved through real
estate leasing or purchase of title.
Renewable Energy Approvals
A REA is now available and regulated by the
Renewable Energy Approvals Regulation
(Reg 359). A REA, which is an approval that is
required for certain renewable energy generation
facilities (REGF), provides an almost “one-window”
approach that combines former requirements
for municipal planning approvals,
environmental assessments, certificates of
approval, permits to take water and other
provincial approvals. The Ministry of Natural
Resources will continue to issue approvals for
renewable energy projects under legislation
that it enforces, but will do so in a manner that
is coordinated with the REA.
Although Reg 359 is too complex and
detailed to cover in its entirety here, the
following are some of the highlights of the
REA process:
- A designated REGF (including
a project such as a solar project
that was not previously required
to obtain an environmental
approval) must obtain a REA.
- A REGF that has obtained required
approvals prior to September 24,
2009, will not be required to obtain
a REA unless or until an amendment
to the approval is required.
- If no approval was required before
September 24, 2009, and construction
of the facility began prior to that
date, a REA will not be required.
- If a notice of completion (under an EA)
for a REGF was issued before September
24, 2009, and the proponent has a
power purchase agreement with
the OPA, a REA will not be required
(i.e., the project would continue on
the approvals path it was on).
- A REGF that obtained a power purchase
agreement with the OPA, was not
prohibited under municipal zoning
and was not subject to Ontario's
Environmental Assessment Act prior to
September 24, 2009, is exempt from
the requirement to obtain a REA.
- Reg 359 exempts certain projects,
such as wind facilities that would
generate less than 3kW, rooftop
and wall-mounted solar facilities,
ground-mounted solar facilities
generating less or equal to 10kW,
and water power projects from the
requirement to obtain a REA.
- Requirements, including a REA, for binergy
facilities that use biomass, biofuel
or biogas material are described, and
depend on location, feedstock and size.
- The REA process requires assessments
related to archaeological, heritage
and natural resources, including
water resources and areas of natural
or provincial significance.
- Reg 359 describes important and
detailed consultation requirements,
including with respect to First Nations.
This includes how notice of and
information related to an application
for a REA, which is designated
as a Class II proposal under the
Environmental Bill of Rights (except for
the appeal rights under Part II of the
EBR, which do not apply to a REA),
must be provided, including posting
on Ontario's Environmental Registry
for a 30-day public comment period.
- Ontario has committed to completing
its review of a REA application within six
months of the date on which the notice
of application is posted on the Registry.
- Under the amendments made to the
EPA, there are certain rights to appeal
the refusal or issuance of a REA.
- Reg 359 describes important
setback requirements, including
for specified wetlands, provincial
parks, conservation reserves, natural
features, and water bodies, which
can potentially be addressed by
environmental impact studies.
- Wind facilities must, in short, meet a
minimum setback of 550 meters from
“noise receptors” (a defined term),
with certain limited exceptions.
- Bio-energy facilities have a
minimum setback of 250 meters
from “odour receptors”, which can
be reduced to 125 meters.
Domestic Content
The FIT program has “Minimum Required
Domestic Content Level” rules that require
certain wind and solar energy project developers
to ensure that a specified percentage
of their facility's project costs come
from Ontario goods and labour by the time
the facility reaches commercial operation.
If a facility does not meet the Minimum
Required Domestic Content Level, the
project developer will be in default under its
FIT contract.
The Minimum Required Domestic Content
Levels are as follows:
- For wind projects with a capacity
greater than 10kW: 25 percent for
facilities with a contracted commercial
operation date before January 1, 2012,
increasing to 50 percent thereafter.
- For solar (PV) projects with a capacity
greater than 10kW: 50 percent for
facilities with a contracted commercial
operation date before January 1, 2011,
increasing to 60 percent thereafter.
- For solar (PV) projects with a capacity
less than or equal to 10kW: 40 percent for
facilities with a contracted commercial
operation date before January 1, 2011,
increasing to 60 percent thereafter.
Domestic Content Level is calculated in accordance
with the draft FIT contract. For
each type of REGF (i.e., either wind or solar)
and capacity, the FIT contract identifies
“Designated Activities” (for example, using
wind turbine blades that have been cast in
a mould in Ontario and have instrumentation
that has been assembled in Ontario)
and a corresponding “Qualifying Percentage”
that a project developer can count towards
its Domestic Content Level if it performs
that Designated Activity in respect of its
facility. The sum of all Qualifying Percentages
allocated to a facility is its Domestic Content
Level.
If a facility is made up of more than one of
the components specified in a Designated
Activity then the Designated Activity must
have been performed in respect of all such
components in the facility. For example, all
turbine blades for a wind project would have
to meet the requirements of the Designated
Activity in order to rely on the Qualifying Percentage.
Next Steps
It is anticipated additional details regarding
the FIT program and other regulatory initiatives
under the Green Energy and Green
Economy Act, 2009 will be forthcoming in
the near term. The Bennett Jones Energy
Group will be distributing timely updates as
necessary.