On June 18, 2019, the Prime Minister announced that the Trans Mountain Pipeline Expansion Project (the "Project"), which involves the twinning of the existing Edmonton (Strathcona)-Burnaby pipeline and the expansion of a marine terminal, was approved, for the second time, by the Federal cabinet.
The Project is one of the largest, most complex and politically-charged projects to be constructed in Canada in the last few decades. Due to increasing political uncertainty in British Columbia, in April 2018, Kinder Morgan (the then-owner of the Project) announced that it was suspending all non-essential work on the Project. The Federal government subsequently purchased the pipeline from Kinder Morgan with a commitment to fund and de-risk the Project, and ultimately sell it back to the private sector.
In August 2018, the Federal Court of Appeal quashed the Certificate of Public Convenience and Necessity (CPCN) granted by the National Energy Board (the "NEB") to Kinder Morgan for the Project. The ruling found that the NEB had erred in its decision to exclude considerations of the environmental impact of project-related marine shipping, and that the Federal government had failed to meet its legal duty to consult with Indigenous peoples. The Court remitted the issue of the Project approval to the Governor in Council for redetermination.
On February 22, 2019, the NEB released its marine reconsideration report, subject to 156 conditions that were ultimately outlined if the Project was subsequently approved by the Federal government, as well as 16 recommendations to federal agencies related to marine shipping that fell outside of the NEB's mandate. The NEB's decision set a three-month deadline for the Federal government to complete its Indigenous consultation requirements and release a final decision on the Project, which was delayed until June 18, 2019.
On June 18, 2019, the Governor in Council once again directed the NEB to issue a Certificate of Public Convenience and Necessity to Trans Mountain ("TM"), the crown corporation holding the Project, subject to the NEB's terms and conditions, including amendments to six of the 156 NEB conditions to further address concerns of Indigenous groups impacted by the Project.
Consistent with reports that the Federal government had been following the roadmap set forth in the Federal Court of Appeal's decision from August 2018, the Prime Minister announced that it acted on the Court's decision and reexamined the impact the Project would have on the marine environment and engaged in a "Phase 3" consultation process with Indigenous peoples led by former Supreme Court Justice, Frank Iacobucci. Below are the key takeaways from the Federal government's decision to proceed with the Project:
Although the Federal government's approval can be viewed as a positive step for the continued development and investment in the Canadian oil industry, the completion of the Project will potentially be met with further challenges.
Indigenous communities in British Columbia, most notably the Tsleil-Waututh Nation, have already indicated potential legal challenges of the Federal government's decision to approve the Project on the basis that the government failed, once again, to adequately discharge its duty to consult.
In addition, the British Columbia government has indicated that it will continue to pursue an appeal to the Supreme Court of Canada of the British Columbia Court of Appeal’s unanimous decision that British Columbia does not have the jurisdictional authority to restrict shipments of heavy oil through the province. Notably, the Supreme Court of Canada is required to hear the appeal as it was sent to the British Columbia Court of Appeal as a reference case.
On June 21, 2019, the NEB issued the amended Certificate of Public Convenience and Necessity for the Project. The NEB has also issued, for public comment, a proposed approach to resume the regulatory process (See NEB seeking Public Comment on Approach to Resume Regulatory Processes for the Trans Mountain Expansion Project). It will continue to be responsible for overseeing TM's compliance with the 156 conditions imposed by the NEB in its report.
In addition, TM is required to apply again for all of the necessary federal, provincial and local government permits. Additional route hearings will likely also be required for certain segments of the Project to allow TM to obtain approval of those portions of its preferred route.
The Federal government has indicated it will explore opportunities for direct Indigenous participation in the Project based on several proposals received during the Phase 3 consultation process.
Timelines for all of these activities have not yet been established; however, construction is still anticipated to recommence in 2019.