On February 1, 2021, the Government of Alberta launched Period 5 and Period 6 of the Site Rehabilitation Program (SRP), including additional information within the updated Site Rehabilitation Guidelines.
As noted in our earlier blog post, following update, and discussions of Period 2, Period 3 and Period 4, the SRP administers funding to eligible oil field service contractors completing reclamation and abandonment work in the province.
As of February 12, 2021, Alberta reports that $310.3 million of the of the $1 billion in federal funding has been approved and is being allocated to 633 Alberta-based companies.
Period 3 (which allocated maximum funding of $139,000 by licensee) and Period 4 (which provided funding for licensees with confirmed and proposed Area-Based Closure Plans) both remain open until March 31, 2021, or until licensee funding has been completely allocated. For more details, please see our earlier discussion of Periods 3 and 4.
With $300 million available, Period 5 represents the largest funding allocation to date. Period 5 will remain open until March 31, 2022, or until allocations are fully subscribed. Funding in Period 5 is available to licensees with confirmed hydrocarbon production in 2019 where the licensees had completed closure work in 2019 and 2020. A list of eligible licensees has been posted online by the Government of Alberta.
Period 5 introduces the opportunity for licensees to use their allocation on sites where they are the Working Interest Participant (WIP). WIPs that are either i) responsible for closure of sites subject to orders issued by the Alberta Energy Regulator (AER); or ii) have a major working interest in a defunct licensee’s site may contract with oil field services contractors to apply for SRP funding starting in Periods 5 and 6. If a contractor applies for and receives funding under the SRP, the WIP will not be eligible to file a Working Interest Claim (WIC) to the AER for that same work on the same site. Any AER abandonment or reclamation order issued to the WIP must be attached to the contractor's contract as part of the SRP grant application. Any active WIC files with the AER are not eligible for an SRP grant.
As in prior SRP periods, oil field service contractors are responsible for applying for funding allocations. However, contractors may now contract with both licensees and WIPs to apply for and obtain SRP funding to complete closure activities.
Similar to Period 4, projects are eligible for 50 percent of the contract value, with the licensee or WIP remaining responsible for the remaining amount. However, where a licensee contracts with an Indigenous oil field service contractor, up to 100 percent of the contract value may receive grant funding. See discussion of Period 4 for guidelines surrounding Indigenous oil field service companies.
Starting in Period 5 and continuing into Period 6, the scope of work in the contractor's oilfield services contract must match the assets and work activities in the SRP grant application project information. If the work and costs do not align, the application will be denied.
Period 6 allocates $100 million in closure funding exclusively for clean-up activities within Indigenous communities in Alberta. The Period 6 application period is open until March 31, 2022, or until allocations are fully subscribed. Funding is divided between First Nations communities ($85 million) and Metis Settlements ($15 million). Lists of eligible licensees associated with First Nations and Metis Settlements are posted online.
First Nations communities and Metis Settlements will approve the sites that are eligible for closure work using their allocation, and will work with licensees and contractors to approve the spending. Once approved, contractors can then apply directly to the Government of Alberta for SRP grants to do the work. First Nations and Metis Settlements cannot apply for this funding—only the contractor doing the work can do so.
As with prior periods, Period 6 closure activity projects are eligible for 50 percent of grant funding, with the licensee or WIP responsible for the remaining amount of the contract. However, and as in Periods 4 and 5, projects may receive up to 100-percent grant funding where a licensee contracts with an Indigenous oil field service contractor to complete the closure work.
In its update to the Site Rehabilitation Program Guidelines, Alberta has clarified a number of points:
Periods 5 and 6 represent the ongoing expansion of the SRP to include larger, longer-term capital injections for a broader variety of closure projects on a greater diversity of land bases. As with prior periods, the effectiveness of the funding roll-out will remain in the details. Given the new timelines, the scope and target of future Periods is unknown at this time.
Should you have questions about the various site rehabilitation programs in British Columbia, Alberta and Saskatchewan, please contact a member of our Regulatory, Aboriginal Law or Environmental Law groups.